An ENERGY STAR partner since 2007, the district invested over 9 million dollars in recommended energy efficiency improvements. There were two broad energy-related areas: 1) the ventilation systems, including air-conditioning, heating, and air circulation (particularly in rest rooms and faculty rooms) and 2) electrical upgrades, including correcting inefficient lighting in large classrooms and hallways and installing additional outlets in various areas of the school for better power supply throughout the building. Funds of over 4 million dollars were invested in other miscellaneous interior improvements.
ENERGY STAR Guidelines for Energy Management were followed throughout the design and procurement of these major capital projects. As a result, the school earned the ENERGY STAR in 2008 for superior energy efficiency. Data compiled through Portfolio Manager continue to help verify that these improvements maximize the use of the school's energy resources.
Communications:
Testimonial:
"Baltz Elementary takes to heart today's ongoing energy conversation and the necessity to change with everyday proactive actions. We applaud Baltz's consistent and dedicated staff who take the extra moment to see each window is closed, the lights are out and that kids grab an extra sweater for winter months."
Please note: Narrative information in this profile has been provided by Red Clay Consolidated School District or a representative of this facility. Other building information was verified and submitted to EPA at the time of application. Building energy performance, operating characteristics, and ownership/management may be subject to change over time.
Service Provider:
Studio JAED Architects & Engineers
Building Owner:*
Red Clay Consolidated School District
Property Manager:*
N/A
Year(s) Labeled (Rating):
2008 (84)
2009 (92)
2010 (88)
2011 (85)
2012 (85)
2013 (78)
2014 (78)
2016 (92)
Facility Type: K-12 School
Total Floorspace: 136278 sf
Year Constructed: 1950
Contract Type: Multiple Vendor Contracts
Financing Type: Public Bond
Technologies Used:
| Stage 1-Recommissioning |
| Stage 2-Lighting |
| Stage 3-Load Reductions |
| Stage 5-Heating and Cooling Plant |
| Other Technologies/Strategies |