First Parish in Needham
23 Dedham Avenue
Needham, MA 02492
Map It!
First Parish in Co-founded with the town in 1711, First Parish is The renovated 15,000-square-foot building, which is 25 percent larger than the old, contains a beautiful and spacious meeting hall, offices, classrooms, and historic sanctuary. Despite its larger size and the addition of air conditioning, the new building has reduced First Parish's utility costs 50 percent and its carbon footprint 43 percent based on actual utility bills. Through this achievement, the church has shown our commitment to environmental stewardship while also lowering our energy costs. Elements that contribute to the building's energy efficiency include: First Parish's commitment to the environment is also shown in its use of materials, such as maple flooring harvested from sustainable forests certified by the Forest Stewardship Council, and paints, carpets, furniture, and other materials chosen for their environmental friendliness. The building is also pre-wired and piped to accommodate a five-kilowatt solar photovoltaic system on the roof to generate electricity. This final addition will mark the completion of the greening of First Parish.
Item Old First Parish New First Parish Reduction
Heat Energy 62,152 BTU/SF/Yr 17,867 BTU/SF/Yr 72%
Electric Energy 19,754 BTU/SF/Yr 28,857 BTU/SF/Yr -46%
Total Energy 81,906 BTU/SF/Yr 46,724 BTU/SF/Yr 43%
Water Consumption 184,756 Gallons 90,508 Gallons/Yr 51%
Greenhouse Gas 11.6 #CO2/SF/Yr 5.3 #CO2/SF/Yr 54%
Utility Costs $1.66/SF/Yr $0.81/SF/Yr 51%
Communications:
The renovation of First Parish in Needham as an example of the Green Sanctuary movement was highlighted in an article published in the Boston Globe on Sunday, October 26, 2008.
Testimonial:
Unavailable
Please note: Narrative information in this profile has been provided by First Parish in Needham or a representative of this facility. Other building information was verified and submitted to EPA at the time of application. Building energy performance, operating characteristics, and ownership/management may be subject to change over time.
Building Owner:*
First Parish in Needham
Property Manager:*
First Parish in Needham
Year(s) Labeled (Rating):
2011 (95)
2010 (94)
Facility Type: House of Worship
Total Floorspace: 15659 sf
Year Constructed: 1836
Contract Type: None
Technologies Used:
| Stage 2-Lighting |
| Stage 3-Load Reductions |
| Stage 4-Fan Systems |
| Stage 5-Heating and Cooling Plant |
| Other Technologies/Strategies |